QuestionQ13

Resource Management

What must be filled in for a resource to be included in capacity planning?

  • A Resource status
  • B Effort
  • C Primary attribute value
  • D Rate model
Explanation

Capacity planning evaluates resource capacity by the selected primary attribute, such as a resource group, role, or skill. A resource therefore needs a populated primary attribute value to be considered.