QuestionQ31

Complementary Practices

Scrum Teams that use Kanban can begin increasing predictability by:

  • A Inspecting and adapting the Product Backlog during the Sprint Review.
  • B Visualizing the Workflow using a Kanban board.
  • C Reducing the amount of work in progress by introducing Work in Progress (WIP) Limits.
  • D Improving transparency by having a CFD, Control Chart and Aging chart.
Explanation

Introducing WIP limits reduces and stabilizes unfinished work. This improves flow and supports more predictable delivery; it is a core Kanban practice for Scrum Teams.