QuestionQ59Verified/Supporting Team EventsCopy linkReport a problemAsk AstroTutorSave questionWhich two timestamps are needed to measure lead time when using a Team Kanban board?Choose twoAWhen the Story is released to users and validatedBWhen the Story is deployedCWhen the Agile Team pulls a Story onto the boardDWhen the Story is accepted by the Product OwnerEWhen the team completes validation of the StoryShow AnswerAnswerExplanationTeam Kanban lead time spans the team-controlled workflow: it starts when the Agile Team pulls a Story onto the board and ends when the Product Owner accepts the completed Story. Deployment, release to users, and user validation occur outside that acceptance boundary or represent subsequent milestones.Learn moreSAFe Team KanbanShow comments0Show commentsCommunity DiscussionNo comments yet. Be the first to start the discussion!