QuestionQ59

VerifiedSupporting Team Events

Which two timestamps are needed to measure lead time when using a Team Kanban board?

Choose two
Explanation

Team Kanban lead time spans the team-controlled workflow: it starts when the Agile Team pulls a Story onto the board and ends when the Product Owner accepts the completed Story. Deployment, release to users, and user validation occur outside that acceptance boundary or represent subsequent milestones.