QuestionQ20
Supporting ART EventsThree teams on the Agile Release Train are working on the same Feature. Team A is a complicated subsystem team, while Teams B and C are stream-aligned teams. During PI Planning, Teams B and C committed to delivering their portions of the Feature by the end of Iteration five and plan to integrate with one another, together with Team A's piece, in the first week of the IP Iteration. Why is this considered an anti-pattern?
- A Because Product Management accepted each team's final plan at the end of PI Planning Day 2
- B Because each feature team needs to integrate with the component team
- C Because the teams managed their dependencies and planned their integration timing during PI Planning
- D Because work should not be planned for the IP Iteration