Three teams on the Agile Release Train are working on the same Feature. Team A is a complicated subsystem team, while Teams B and C are stream-aligned teams. During PI Planning, Teams B and C committed to delivering their portions of the Feature by the end of Iteration five and plan to integrate with one another, together with Team A's piece, in the first week of the IP Iteration. Why is this considered an anti-pattern?