Why is the program predictability measure the main metric used during the quantitative-measurement portion of the Inspect and Adapt event?
The Program Predictability Measure compares planned and actual business value across the Agile Release Train’s teams, making it the key indicator of the ART’s performance and reliability in delivering business value during the PI timebox.