QuestionQ1

VerifiedIntroducing Scrum in SAFe®

How is the average lead time measured in a Kanban system?

Explanation

Average lead time is the elapsed time from a work item entering the system to leaving it. On a cumulative flow diagram, time is plotted on the horizontal axis, so this is represented by the horizontal distance between the arrival and departure lines.