QuestionQ19

VerifiedSupporting Team Events

During which of the following Agile Team events do team members estimate the relative sizes of stories?

Explanation

Backlog Refinement is the event in which Agile team members clarify upcoming stories and estimate their relative size, commonly using story points. Those estimates support subsequent iteration planning.