QuestionQ9

Agile Product Delivery

Which of the following is an example of applying cadence and synchronization in SAFe?

Explanation

PI Planning is a recurring, cadence-based event that brings Agile Release Train teams together to align on objectives, plans, risks, and dependencies for the Program Increment. This shared planning event directly reinforces cadence and synchronization.