QuestionQ7

Lean Portfolio Management

Which two items does the program board display?

Choose two
  • A Risks
  • B Capacity and load
  • C Significant dependencies
  • D Features
  • E Epics
Explanation

A SAFe Program Board/ART Planning Board visualizes PI feature delivery dates and dependencies among teams. Therefore, the applicable items are features and significant dependencies.