QuestionQ45
VerifiedAgile Product DeliveryAt the end of PI Planning, after dependencies have been resolved and risks addressed, a confidence vote is held. What default voting method is used?
At the end of PI Planning, after dependencies have been resolved and risks addressed, a confidence vote is held. What default voting method is used?