Which statement is accurate about ART events?

  • A ART events run inside the team events, and the team events create a closed-loop system
  • B Team events run inside the ART events, and the ART events create a closed-loop system
  • C The Inspect and Adapt is the only ART event required to create a closed-loop system
  • D The daily stand-up is an ART event that requires the scrum of scrums and Program Owner sync involvement in the closed-loop system
Explanation

ART events provide the coordination and feedback loop across the Agile Release Train, while individual team events occur within that ART-level operating cadence. Together, these ART events create a closed-loop system for alignment, execution, and improvement.