QuestionQ51
Manage Scheduling and OptimizationUniversal Containers carries out multistage projects in which the second job can begin only after the first job is completed.
How should a Consultant recommend implementing this process?
- A Create two Service Appointments and set the Start after Finish dependency between them.
- B Create two Service Appointments and schedule them to the same Resource.
- C Create one Service Appointment and schedule it to two different Resources.
- D Create one Service Appointment with the total duration of the two jobs and assign two Resources.