QuestionQ89

VerifiedApplication Lifecycle Management

Universal Containers’ (UC) development team uses an Agile tool to track build-item status, but only by stage. UC cannot track effort estimates, record hours worked, or monitor remaining effort.

Why should UC reconsider using the Agile tool to track effort?

Explanation

Recording estimated effort alongside actual and remaining effort lets developers assess the accuracy of their estimates and refine future estimates. Agile planning is iterative, with time and cost estimates defined and refined as requirements are elaborated.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!