QuestionQ48

Environments

Universal Containers plans a release strategy with major releases every four weeks and minor releases every week. Major releases progress through Development, System Integrated Testing (SIT), User Acceptance Testing (UAT), and Training. Minor releases progress through Development and UAT.

What is a valid environment-strategy consideration for UAT?

  • A Minor releases use Partial copy and Major releases use Full copy.
  • B Minor releases use Developer and Major releases use Full copy.
  • C Minor and Major releases use the same Full copy.
  • D Minor and Major releases use separate Developer pro.
Explanation

A Partial Copy sandbox includes metadata and selected sample production data and can be refreshed every 5 days, making it suitable for weekly minor-release UAT. A Full sandbox includes all production data and has a 29-day refresh interval, which aligns with a four-week major-release cycle and supports major-release UAT and training.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!