QuestionQ15

Testing

Universal Containers (UC) is preparing for a large data migration as part of its Service Cloud implementation. UC has approximately 15 million customers, 30 million contacts, and 30 million active cases.

Which two key areas should UC include in its data-migration test plan?

Choose two
  • A APIs to be used for data migration
  • B Target Salesforce Server and Source system IP address
  • C Manual and Automated data validation approaches
  • D Success criteria for data migration
Explanation

A migration test plan needs validation methods to confirm that record counts, field values, relationships, and data quality were preserved, using appropriate manual and automated checks. It also needs clear success criteria so stakeholders can determine objectively whether the migration is complete and acceptable.