A project is beginning its third of six iterations. During planning, the team discovers that not all requirements are defined clearly enough to begin work.

What should the project manager do?

Explanation

The product owner is accountable for ensuring Product Backlog items are clear, transparent, and understood. Product Backlog refinement further defines items so the team has sufficient clarity to select and plan work for an iteration. Reviewing the backlog with the product owner is therefore the appropriate action. The Scrum Guide

Learn more