At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?

Explanation

Action item management requires prioritization, assignment of responsibility, and progress tracking. This systematic approach ensures alignment with project priorities and establishes accountability. Deferring actions (option A) risks losing momentum; updating schedules without prioritization (option C) can create unrealistic plans; immediate follow-up (option D) without prioritization may waste effort on low-impact items.