Loading questions...
Updated
Want a break from the ads?
Become a Supporter and enjoy a completely ad-free experience, plus unlock Learn Mode, Exam Mode, AstroTutor AI, and more.
A risk manager assessed all project risks, and the team is now identifying common groupings of risks. What tool or technique is used to perform this risk assessment?
A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?
The risk manager is currently performing the monitoring and reporting process. Which of the following is an input for schedule metrics?
The project manager generates a monthly risk report for key stakeholders which documents high and medium risk items only. Where would the project manager find the list of recipients for the report?
The risk manager is documenting the results of the Monitor Risks process to add them to the lessons learned database.
A ) Effectiveness of risk response
B ) Unexpected or undocumented risks which occur
C ) Relevant risk data -
D ) Management reserve report -
Which of the following should be included?
The project manager asks the risk manager to determine the initial risk assessment for a six month conduct the related analysis? (Choose two.)
A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.
Which data analysis tool should the risk manager use to forecast future performance?
A risk manager schedules a project overview meeting with the project sponsor to provide an update on risk management progress. Each functional lead is identifying the most critical information to be presented at an executive level. The information must balance communicating essential information with actions and recommendations.
What risk information should be communicated to the project sponsor?
After years of experience, a project manager becomes the lead manager for a company. This new lead manager asks all project managers to use a specific technique when they perform qualitative risk analysis on their projects. This technique consists of achieving the relative weighting of the project's objectives in terms of priority to the stakeholders.
What is the name of this technique?
Which of the following should the risk manager consider as external environmental factors when creating the risk management plan?

The project manager has asked for the P50 estimate for the project schedule. What is the P50 estimate?
The project manager needs to create a risk management plan for a high risk project, but the company's senior management does not see value in spending time documenting major risks instead of leading the project. What is the most appropriate action for the project manager to take first?
What is the purpose of mitigating negative risks as a part of the risk response process?
A risk on the risk register is triggered. This triggered risk costs US$200,000 to mitigate and will overwhelm the project, causing it to fail if not mitigated. The project manager identifies that there is US$200,000 left in the management reserve.
From which of the following sources should the funds be drawn to cover the risk mitigation?
The risk manager is about to go on medical leave, but before departing, conducts a risk response planning review meeting with stakeholders. A new risk manager is assigned to the project, and during the first status meeting an issue is identified.
What is the appropriate course of action in this case?
A mobile operator wants to test a new network prototype before conducting full implementation on the entire network. What type of risk response strategy did the mobile operator choose?
The team has just completed a risk response planning session and identified responses for all the high and medium priority risks. What should the team do with the remaining low priority risks?
Which of the following represents the best description of the role of project manager for project risk management?
During what process should a project manager assign a risk owner?
PESTLE, TECOP, and SPECTRUM are three examples of prompt lists that can be used during risk management activities. Prompt lists are used to do which of the following?
A project in the execution phase at the customer's site has an issue concerning new parts that do not fit properly into a machine. The site project manager cannot find this high probability risk in the risk register.
What action should the site project manager take?
The project manager is unable to obtain a global consensus of competing subject matter experts and stakeholders on the project scope. This has caused a one- month delay.
What should the project manager do next to reduce further delay?
Within the organizational process assets, where would the project manager find risk response effectiveness from past projects?
After a risk review meeting, three key risks are identified as likely to be realized. The project manager requests a risk scenario be calculated to establish the impact on the budget.
What is the forecasting methodology that should be utilized to calculate the impact?
A heavy industrial design firm has over USS3 billion in current contract value. As a result of quantitative risk analysis of a geographically separated project, opportunities have been identified and assessed as high priorities for the project.
What is the most effective method to capture these opportunities?