When managing a product backlog, which statement best describes how to determine the value of backlog items?
AThe stakeholders provide recommendations with the product owner having the final say.
BThe stakeholders follow the value-ranking criteria.
CThe stakeholders provide input about backlog value when the item is first identified.
DThe stakeholders do not typically play a major role.
A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting. The stakeholder insists that these requirements must be taken into account despite time and budget constraints.
What is the most effective way to manage this situation?
APostpone the baseline approval meeting, analyze the impact, and schedule a new meeting to discuss dependencies and priorities with stakeholders.
BShare the new requirements with all stakeholders and ask them to submit their comments before the meeting.
CAsk for more resources to manage this change and justify these additional resources with the value the change will give to the company.
DDiscuss the change with stakeholders during the baseline approval meeting and ask them to approve the new baseline.
A project affects the marketing unit and procurement unit. The project manager gives the business analyst an overview of the project for the first time.
What should the business analyst do immediately after the discussion?
ASchedule time with the process owners.
BDevelop an issues log.
CPut the information into a project plan.
DAssess the risks for the project.
A company wants to procure a tool to improve customer satisfaction and loyalty. Which of the following documents would provide basis for analyzing vendor products?
ABusiness case
BProject charter
CSurvey
DStoryboard
Question 6
Domain 3. Analysis
0
Question 7
Domain 1. Needs Assessment
Question 8
Domain 2. Planning
Question 9
Domain 2. Planning
Question 10
Domain 3. Analysis
Question 11
Domain 1. Needs Assessment
Question 12
Domain 3. Analysis
Question 13
Domain 2. Planning
Question 14
Domain 3. Analysis
Question 15
Domain 4. Traceability and Monitoring
Question 16
Domain 3. Analysis
Question 17
Domain 2. Planning
Question 18
Domain 1. Needs Assessment
Question 19
Domain 4. Traceability and Monitoring
Question 20
Domain 4. Traceability and Monitoring
Question 21
Domain 4. Traceability and Monitoring
Question 22
Domain 5. Evaluation
Question 23
Domain 1. Needs Assessment
Question 24
Domain 1. Needs Assessment
Question 25
Domain 2. Planning
Ask AstroTutor
0
Ask AstroTutor
0
Ask AstroTutor
0
Ask AstroTutor
0
Ask AstroTutor
0
Ask AstroTutor
0
Ask AstroTutor
0
Ad
Want a break from the ads?
Become a Supporter and enjoy a completely ad-free experience, plus unlock Learn Mode, Exam Mode, AstroTutor AI, and more.
Ask AstroTutor
0
Ask AstroTutor
0
Ask AstroTutor
0
Ask AstroTutor
0
Ask AstroTutor
0
Ask AstroTutor
0
Ask AstroTutor
0
Ask AstroTutor
0
Ask AstroTutor
0
Ask AstroTutor
0
Ask AstroTutor
0
Ask AstroTutor
0
How can a SWOT analysis help when deciding between several possible options to address a business problem?
AIt can help the project sponsor to determine the valuation of each option.
BIt can help the stakeholders identify the strengths and weaknesses of each option.
CIt can help the product owner to determine opportunity cost of not choosing an option.
DIt can help the stakeholders to determine how to avoid the threats of each option.
A business analyst has been assigned to a project to implement a new phone system for a customer call center. The business analyst will need to create a business case.
Which of the following components will the business analyst use as input to the business case?
AProduct scope
BWork breakdown structure
CProject timeline
DProject scope
What is a standardized, effective, and efficient way to manage changes to project documentation?
AA change control board
BA requirements traceability matrix
CA configuration management system
DA configuration verification and audit system
Company A would like to enter into a new market. The business analyst has been assigned to a project for which nobody in Company A has any prior experience. The project manager has asked the business analyst to assist in resource planning.
What should the business analyst recommend to the project manager?
AAsk the sponsor for more resources.
BReview the business case to reconsider the project.
CAsk the developer’s team manager for more resources.
DHire external subject matter experts for the core project team.
Which tool provides combined functionality for business analysis and quality assurance activities?
AFunctional specification tool
BSolution quality assurance tool
CSystem use case modeling tool
DRequirements traceability tool
A type of requirements document that would be the most valuable to a database administrator would be:
Aan object diagram.
Ban entity relationship diagram.
Ca business process diagram.
Da data flow diagram.
A company wants to improve the service to its customers by reducing complaint response time by 40%. To achieve this goal, it is necessary to redesign and optimize their internal processes and support it with a new product. The client thinks that disruption and short-term loss of productivity is inevitable.
Where can the business analyst best reflect the intangible costs associated with this change?
AIn the requirements specification document
BIn the balanced score card chart
CIn the pay-back analysis
DIn the business case
The quality function deployment is best suited to assist in the process of:
Aquality assurance by structuring the quality audits.
Brelating the product features to customer value.
Cquality control by determining the control charts and the run charts.
Dcontrolling the effects between the quality functions.
The following requirement was included in a business requirements document: “An API shall be built to send data back and forth from the accounting system to the customer relationship system so that name and address data can be synchronized.” What should be done with this business requirement?
AIt should remain because it specifies the reason why the business requirement is needed.
BIt should be revised because it states a solution to the problem rather than the business need.
CIt should be removed because it does not state how often the data should be synchronized.
DIt should remain because it specifies the type of data and the source system.
A business analyst and stakeholders have completed documentation of the acceptance criteria for the requirements of a new vehicle leasing database. A concern is raised that some of the key performance indicators may not validate the desired benefits of the implementation.
What should the business analyst do to ensure that the business need can be validated?
ADocument a constraint
BDocument a defect
CDocument an assumption
DDocument a business rule
When modeling processes or analyzing tasks, business rules can be uncovered by asking about:
Awork that may be performed out of sequence.
Breasons for choosing a particular course of action.
Ctasks that overlap with each other.
Dtask transitions that hinder organizational performance.
The customer generated a design specification for a new product. What is the best action to take to establish an approved requirements baseline with the customer?
ACreate a requirements traceability matrix for review and approval by the customer.
BCreate a requirements baseline approval form for the customer to review and approve.
CRequest that the customer create a baseline of the requirements in the contract specification.
DPerform a variance analysis on the design specification and report the results to the customer.
A document is being created that will detail the customer’s needs for a product and will include a functional model, a data model, and a glossary of terms. This document is called a:
Abusiness case.
Brequirements specification.
Cproject charter.
Dstandard operating manual.
The requirements traceability matrix should primarily be used to:
Aidentify the risks associated with dependent requirements.
Baddress the responsibility owner for each requirement.
Censure that all requirements have been met.
Ddefine a convention to map the requirements to their sources.
In the first few weeks after a large implementation of a new web-based application, a critical report failed. Further investigation determined that a worker had been using a field that was not supposed to be used. This issue was not identified in testing.
Which technique could have prevented this problem from occurring?
APrototyping
BUse cases
CDocument analysis
DDiagrams
Requirements for a project have already been approved and finalized when a stakeholder approaches the project team with a change to one of their requirements. Which method of document control should the business analyst use to document changes in requirement(s) versioning?
AProject plan
BStatement of work
CTraceability matrix
DProblem or opportunity statement
A company has launched a new online sales application and engaged a focus group to test how quickly the customer could place an order. The focus group also provided feedback on their satisfaction.
Which metrics tool should the business analyst use to record the results?
AFocus group
BBusiness completion
CCustomer
DSales and marketing
After reviewing a business case, project goals, and objectives, a business analyst determines that the organization prefers taking an exploratory approach to finding the solution that best meets the business need. Which approach best aligns with the business need for this organization?
AChange-driven approach
BAnalytical approach
CWaterfall approach
DPlan-driven approach
A business analyst conducts an initial review to define scope. The analysis includes the review of the business case, project goals, and objectives to obtain the necessary and required context. Based on that information, the business analyst determines that this is a large project with multiple interfaces which could cost the company money that was not initially included in the budget.
What characteristics of the project are needed to determine the approach so that the business analyst can validate whether they will need to have a discussion about the budget?
ASelected project life cycle
BBusiness analysis deliverables to be produced
CType of elicitation activities to be conducted
DDecision on the type of models to be used
A business analyst is planning the business analysis activities for a new payroll project. Due to a tight timeline, the analyst advises stakeholders that the requirements sessions should begin as soon as possible.
Which key factor drives the selection of business analyst activities to be included in the project?