QuestionQ81
DeliverySenior management is frustrated by the absence of a detailed implementation plan that shows precisely when the project will finish and when all requirements will be satisfied.
The team has used a rolling wave planning approach so far on the project. How should the agile practitioner explain the benefits of this approach to senior management?
- A It ensures a consistent level of detail is available in the project schedule
- B It prevents a wasteful build-up of requirements inventory that may never be processes
- C It provides a concrete definition of product scope, cost and duration
- D It allows the team to lock down the stories to be included in a release