QuestionQ81

Delivery

Senior management is frustrated by the absence of a detailed implementation plan that shows precisely when the project will finish and when all requirements will be satisfied.

The team has used a rolling wave planning approach so far on the project. How should the agile practitioner explain the benefits of this approach to senior management?

  • A It ensures a consistent level of detail is available in the project schedule
  • B It prevents a wasteful build-up of requirements inventory that may never be processes
  • C It provides a concrete definition of product scope, cost and duration
  • D It allows the team to lock down the stories to be included in a release
Explanation

Rolling wave planning details work only when it is close enough to execution for the information to be reliable. This reduces waste from building and maintaining a large inventory of detailed requirements that may change or never be needed.