QuestionQ80
DeliveryDuring an iteration, an agile team identifies infrastructure requirements that were not considered initially.
What should the team do to manage these effectively?
- A Rework the iteration scope to accommodate these requirements
- B Add these requirements into the product backlog for future consideration
- C Raise the discovery of these requirements as an issue, and escalate to management
- D Immediately start working on these requirements
Community Discussion