QuestionQ389

Delivery

Question Image

The team manager is accountable for delivering a particular initiative within the organization. They are preparing for the monthly project-review meeting, where they will present the initiative’s current status. The agile project lead sends the manager the following email with the initiative’s current status.

Which summaries are correct and will be presented at the monthly project review? (Refer to the email and exhibits to the Team Manager)

  • A MVP has 25 remaining story points; MVP will complete at the end of sprint 8; with no other deviations, the entire backlog will complete at the end of sprint 15.
  • B MVP has 30 remaining story points; MVP will complete at the end of sprint 8; with no other deviations, the entire backlog will complete at the end of sprint 15.
  • C MVP has 25 remaining story points; MVP will complete at the end of sprint 9; with no other deviations, the entire backlog will complete at the end of sprint 16.
  • D MVP has 30 remaining story points; MVP will complete at the end of sprint 9; with no other deviations, the entire backlog will complete at the end of sprint 16.
Explanation

The unfinished MVP work totals 30 story points: 4 for accessibility, 21 for increased security, and 5 for the AI chatbot. The backlog contains 72 story points in total, of which 10 are complete. Applying the remaining-story-point trend and the forecasted holiday-related reduction in burn yields MVP completion at the end of sprint 9 and completion of the full backlog at the end of sprint 16.