QuestionQ389
Delivery
The team manager is accountable for delivering a particular initiative within the organization. They are preparing for the monthly project-review meeting, where they will present the initiative’s current status. The agile project lead sends the manager the following email with the initiative’s current status.
Which summaries are correct and will be presented at the monthly project review? (Refer to the email and exhibits to the Team Manager)
- A MVP has 25 remaining story points; MVP will complete at the end of sprint 8; with no other deviations, the entire backlog will complete at the end of sprint 15.
- B MVP has 30 remaining story points; MVP will complete at the end of sprint 8; with no other deviations, the entire backlog will complete at the end of sprint 15.
- C MVP has 25 remaining story points; MVP will complete at the end of sprint 9; with no other deviations, the entire backlog will complete at the end of sprint 16.
- D MVP has 30 remaining story points; MVP will complete at the end of sprint 9; with no other deviations, the entire backlog will complete at the end of sprint 16.
Community Discussion