QuestionQ388
ProductA scrum master belongs to a team that has just reached agreement on the project scope and deliverables for a global, multilingual manufacturing company with many staff members who move between locations. The team has 20 people, and the budget is US$5 million. The kickoff meeting is planned for the following month.
What should the scrum master do first?
- A Organize a sprint planning meeting and include stakeholders.
- B Invite the product owner to create a stakeholder map.
- C Identify the key stakeholders at the earliest opportunity.
- D Invite the key stakeholders to the kickoff meeting.