QuestionQ388

Product

A scrum master belongs to a team that has just reached agreement on the project scope and deliverables for a global, multilingual manufacturing company with many staff members who move between locations. The team has 20 people, and the budget is US$5 million. The kickoff meeting is planned for the following month.

What should the scrum master do first?

  • A Organize a sprint planning meeting and include stakeholders.
  • B Invite the product owner to create a stakeholder map.
  • C Identify the key stakeholders at the earliest opportunity.
  • D Invite the key stakeholders to the kickoff meeting.
Explanation

Key stakeholders should be identified at the earliest opportunity. Early identification enables appropriate analysis, engagement, communication planning, and participation in subsequent project activities.