QuestionQ194
ProductDuring a review session, an agile team demonstrated completed requirements to a group of stakeholders. Stakeholder feedback showed that the completed requirements did not address the most pressing needs or deliver value.
What should the team have done to avoid this?
- A Reprioritized requirements prior to committing to iteration work
- B Ensured that requirements remained stable during the iteration cycle
- C Had stakeholders focus on items created after the product backlog was initially built
- D Worked on features rather than a set of components