QuestionQ194

Product

During a review session, an agile team demonstrated completed requirements to a group of stakeholders. Stakeholder feedback showed that the completed requirements did not address the most pressing needs or deliver value.

What should the team have done to avoid this?

  • A Reprioritized requirements prior to committing to iteration work
  • B Ensured that requirements remained stable during the iteration cycle
  • C Had stakeholders focus on items created after the product backlog was initially built
  • D Worked on features rather than a set of components
Explanation

Agile teams should order or reprioritize requirements before committing iteration work so that the selected items address the most urgent stakeholder needs and maximize delivered value. The Product Backlog is an ordered list of work, and the Product Owner is accountable for maximizing product value.