QuestionQ193

Delivery

A member of a cross-functional agile team has been unable to complete assigned work because the functional manager has assigned tasks.

What should the Scrum Master do?

  • A Dismiss the team member
  • B Discuss the situation with the functional manager
  • C Report the functional manager to the project sponsor
  • D Demand that the functional manager respect the project charter
Explanation

A Scrum Master helps remove impediments that prevent the team from completing its work. Conflicting assignments from a functional manager should be addressed through collaboration with that manager to clarify priorities and protect the team’s ability to deliver.