CAPM: Certified Associate in Project ManagementDemo
By PMI · Browse Mode
//
QuestionQ1
Project Management Fundamentals and Core Concepts
CAPM: Certified Associate in Project Management PMI Practice Exam
Save question
Guiding another person from one point to another through a known set of expected behaviors, while being able to lead a team and inspire them to perform their jobs effectively, relates to?
AInfluence and challenge
BInnovation and administration
CLeadership and management
DEngagement and guidance
0
Community Discussion
No comments yet. Be the first to start the discussion!
QuestionQ2
Project Management Fundamentals and Core Concepts
0
Community Discussion
No comments yet. Be the first to start the discussion!
QuestionQ3
Project Management Fundamentals and Core Concepts
0
Community Discussion
No comments yet. Be the first to start the discussion!
QuestionQ4
Project Management Fundamentals and Core Concepts
0
Community Discussion
No comments yet. Be the first to start the discussion!
QuestionQ5
Project Management Fundamentals and Core Concepts
0
Community Discussion
No comments yet. Be the first to start the discussion!
It's free
100% of the questions are free for all users. No strings attached.
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
A project team has finished the sprint review, and users are impressed by the demonstration. However, another functionality included in the sprint, which was not discussed during the review, is not ready for production deployment.
What should the project team do?
ADemo the incomplete feature at the sprint retrospective.
BDeploy the functionality that was presented to the users.
CContinue with sprints until the product backlog is empty.
DWait to complete all user stories that are in development.
Which Project Schedule Management process identifies and documents the specific actions that must be performed to produce a project’s deliverables?
APlan Schedule Management
BDefine Activities
CDevelop Schedule
DEstimate Activity Durations
During the elicitation phase, a product owner requests a change to one of the requirements. What should the business analyst do?
AProvide the information to the product manager for approval.
BProvide the information to the project manager to seek approval or rejection.
CAccept the modification and update the requirements traceability matrix.
DReject the change as the project scope has already been defined.
Company A has just been informed of a new legal requirement affecting its business operations. How is this item classified?
AInternal enterprise environmental factor
BRisk register database
CExternal enterprise environmental factor
DOrganizational process asset
Which approach is recommended for managing risk in a highly variable environment?
AAdaptive
BPredictive
CIterative
DIncremental
A project manager is developing a monthly project status report that includes project performance against the baseline schedule. How can the project manager calculate schedule variance (SV) for tasks on the critical path?
AEarned Schedule ÷ Actual Time
BActual Time - Earned Schedule
CEarned Value - Planned Value
DPlanned Value - Earned Value
Lucia, the product owner, confirms that the final deliverables have just been approved and are right on schedule. Lucia will meet with the client to share the good news. After the news is presented, the client requests that an additional feature be added.
What documentation should Lucia have obtained after the final deliverables were approved?
ALessons learned
BProject management plan
CSign-off
DScope definition
Determining the phases of a project life cycle is considered part of which knowledge area?
AProject Schedule Management
BProject Scope Management
CProject Resource Management
DProject Integration Management
What are the principal tools used to manage project knowledge?
AExpert judgment and data gathering
BNetworking and storytelling
CData analysis and decision making
DPrototypes and product analysis
What key qualities should project managers possess for strategic and business management?
ASkills and behaviors related to specific domains of project management
BKnowledge and competencies needed to guide and motivate a team
CSkills and behaviors needed to help an organization achieve its goals
DExpertise in the industry and organization that deliver better outcomes
Who is accountable for developing the business case document?
AProject manager
BProject stakeholders
CProject team
DProject sponsor
A project obtains budget approval, but there is an anticipated risk of additional costs. Which inputs should the project manager review to perform a qualitative risk analysis?
AThe risk management plan and the assumption log
BCosts estimates and cost forecasts
CThe risk management plan and the basis of estimates
DThe assumption log and the project charter
A project is estimated to take 10 months and has a total budget of US$220,000. At the end of month five, the project is projected to incur US$250,000 at completion.
If the calculated actual cost (AC) is US$150,000, what is the project's earned value (EV)?
AUS$-30,000
BUS$120,000
CUS$370,000
DUS$400,000
A new vendor provides a one-time price reduction but cannot guarantee continued presence in the local market for future projects. Which project management approach should be used to benefit from this offer?
AAgile
BPredictive
CHybrid
DIterative
Who identifies the project requirements during the project’s early phase?
AProject sponsor, business analyst, and key stakeholders
BProject manager, business analyst, and key stakeholders
CBusiness analyst, product team, and key stakeholders
DProject manager, business analyst, and project sponsor
At a kickoff meeting, the project sponsor introduces a highly ambitious project. Unfortunately, stakeholders are not very enthusiastic because the work required for the new project appears inefficient.
What might be absent from the business case?
AApproval from the stakeholders
BRoot cause analysis of the problem
CWork breakdown structure (WBS)
DFeasibility study of the solution
What is one tailoring consideration when applying Project Risk Management processes?
AProject complexity
BProcurement criteria
CCommunication technology
DKnowledge management
A team has been assigned to design a product that addresses a problem it has never encountered before. The project team is struggling to gain traction because the solutions are unclear.
What should the project manager do next?
AAdd the issue to the project issue log, as it will impact the project performance.
BAdd the risk to the project risk register, as the lack of solutions could impact how the product is built.
CFacilitate a brainstorming session for the team to discuss ideas to solve the problem.
DMeet with the project sponsor to understand their vision on how to address the problem.
An adaptive team is conducting its kickoff meeting and planning the project management approach. After defining project events, a team member says that the artifacts are missing. The project manager coaches the team to complete the planning.
Which two of the following items should be included in the planning?
Choose two
ASprint backlog
BIncrements
CDaily scrum
DSprint retrospective
ESprint review
During a project team meeting, a team member proposes a product functionality that would greatly benefit the customer. The project manager records the request for later analysis.
Community Discussion