QuestionQ74

VerifiedFoundation and Cluster Deployment

Refer to the exhibit.

Question Image

A Foundation installation must be performed on four NX nodes for a new customer. A consultant needs to configure the onsite network before imaging the nodes with the Foundation tool.

The nodes have two dual-port SFP28 25GbE NICs and a dual-port 10GBase-T NIC. The customer’s ToR switches are 25GbE datacenter switches that are already in production.

What hardware is appropriate to perform the most reliable imaging of these NX nodes?

Explanation

Foundation imaging requires the Foundation workstation to reach each node’s BMC/IPMI interface and a host data interface. Four nodes therefore require eight node Ethernet connections; the Foundation laptop requires a ninth. An isolated flat Ethernet switch provides the required Layer-2 connectivity without introducing dependencies on the active production ToR environment or DAC/SFP28 compatibility. Nutanix Foundation supports discovery and imaging through a flat switch.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!