QuestionQ65

VerifiedFoundation and Cluster Deployment

After an on-site cluster deployment, a consultant prepares the deliverables for project closeout.

Which two data items in the As-Built Guide need adjustment or may be completely absent?

Choose two
Explanation

The Nutanix Node Port Layout and Physical Rack Layout document the actual physical implementation: final node-to-switch cabling, port use, and rack placement. These details can change during installation and may not be captured automatically, so they must be verified and updated as part of the as-built deliverable.