QuestionQ15

VerifiedFoundation and Cluster Deployment

A consultant must confirm the make and model of the systems that will be imaged with Foundation. The consultant does not have the BOM available for review.

When should the consultant confirm the make and model in preparation for the cluster deployment?

Explanation

The system make and model must be confirmed during the kickoff call so that hardware-specific compatibility and imaging requirements can be prepared before the on-site cluster deployment. Confirming it only on arrival or during Foundation leaves insufficient time to prepare the required deployment resources.

Community Discussion

No comments yet. Be the first to start the discussion!