QuestionQ81

Manage VMs within a Nutanix Multicloud Environment

An administrator wants to plan for new project-related growth.

New project workload requirements have been added for a cluster named ClusterXYZ:

  • 2 medium-sized SQL Servers
  • 10 VMs with 16 GB RAM, 4 vCPU, and 100 GB Storage

Which two additional information items should be included in the capacity-planning scenario to provide an appropriate capacity-runway expectation?

Choose two
  • A Date(s) workload(s) will be added
  • B Existing cluster hardware specifications
  • C Change in Demand percentage
  • D Storage compression ratio(s) for new workload
Explanation

A capacity-runway forecast must model when the new workloads will be introduced and how their resource demand is expected to grow over time. Those inputs determine the projected date at which available cluster capacity will be exhausted.