The customer plans to maintain a cluster runway of 9 months. Although the customer lacks budget for 6 months, they want to add new workloads to the existing cluster. Based on the exhibit, what is required to meet the customer's budgetary time frame?

Explanation

With only 66 days of current runway, starting additional workloads would further reduce the remaining capacity period. Because additional cluster resources cannot be funded within the stated budgetary time frame, the new workloads must be deferred.