QuestionQ21Verified/Nokia DC Fabric solutionCopy linkReport a problemAsk AstroTutorSave questionWhich of the following is not included in Day 2+ operations with Nokia’s Fabric Services System?AMonitor the data center fabric using model-driven telemetry.BAnalyze the overall health of the data center fabric for proactive operations.CUse the digital sandbox to test and validate configuration changes and upgrades.DUse a fabric intent to build and validate design templates.Show AnswerAnswerExplanationDay 2+ activities occur after initial deployment and include telemetry monitoring, state monitoring, and subsequent fabric reconfiguration. Creating and validating fabric design templates through a fabric intent belongs to the pre-deployment planning and design lifecycle, which Nokia classifies as Day 0.Learn moreNokia Fabric Services System OverviewShow comments0Show commentsCommunity DiscussionNo comments yet. Be the first to start the discussion!