QuestionQ59Verified/SAN implementation and configurationCopy linkReport a problemAsk AstroTutorSave questionWhich three tasks should be performed as part of site preparation for installation?Choose threeAplan zoning configurationBverify equipment move pathCdetermine aggregate layoutDverify power drops in the equipment locationEmake contact with data center personnelShow AnswerAnswerExplanationSite preparation ensures that equipment can be delivered to its location, that the required electrical infrastructure is available there, and that the appropriate data-center contacts are coordinated before installation. Storage zoning and aggregate-layout planning are configuration or design activities rather than physical site-readiness tasks.Show comments0Show commentsCommunity DiscussionNo comments yet. Be the first to start the discussion!