You are creating a Fabric notebook named MasterNotebook1 in a workspace. MasterNotebook1 includes the following code.

Question Image

You need to make sure the notebooks run in this sequence:

  1. Notebook_03
  2. Notebook_01
  3. Notebook_02

Which two actions should you take? Each correct answer is part of the solution.

NOTE: Each correct selection is worth one point.

Choose two
Explanation

mssparkutils.notebook.runMultiple() executes notebooks according to the dependencies defined in the DAG, not the order they're declared or the concurrency setting — with concurrency allowing parallel execution, only explicit dependency edges enforce ordering. Adding a dependency that ties Notebook_01's execution to Notebook_03 finishing first, and a dependency that ties Notebook_02's execution to Notebook_01 finishing first, is what forces the required 03 → 01 → 02 sequence.