You have a Storage Spaces Direct cluster in a hyper-converged deployment. The cluster has three nodes running Windows Server 2022 and hosts 20 Hyper-V virtual machines.

You must upgrade the servers to Windows Server 2025. The solution must meet these requirements:

  • Minimize virtual-machine downtime.
  • Minimize administrative effort.

Which four actions should be performed on each node, in sequence?

Drag & Drop
Explanation

A rolling Storage Spaces Direct upgrade processes one node at a time. Draining a node migrates its clustered workloads, including VMs, before the node is put into storage maintenance mode. An in-place upgrade retains the node’s configuration and cluster membership, reducing administration. After the upgrade, disable storage maintenance mode and resume the node so it can rejoin normal cluster operation.