You need to deploy a 5-stage IP Clos campus fabric, using claim codes for every switch. Which two statements are true about this process?

Choose two
Explanation

Claim-code-based deployment permits the switches to be claimed and provisioned when they subsequently boot and connect, so they do not have to be online when the Campus Fabric wizard is started. Each switch must be assigned to the site that will host the campus fabric, because site assignment associates the device with the applicable site configuration and provisioning context.