QuestionQ95Verified/Chapter 5: Managing the Test ActivitiesCopy linkReport a problemAsk AstroTutorSave questionWhich ONE of the following items is TYPICALLY included in the test plan?AThe budget and schedule for the test project.BA detailed analysis of the defects found and their causes.CA detailed report on the test results after the test project is completed.DA list of test logs from the test execution.Show AnswerAnswerExplanationA test plan normally defines how testing will be conducted and the resources and timing required, including the test project’s budget and schedule. Defect analyses, final test reports, and test logs are produced as testing progresses or concludes.Show comments0Show commentsCommunity DiscussionNo comments yet. Be the first to start the discussion!