QuestionQ83Verified/Chapter 5: Managing the Test ActivitiesCopy linkReport a problemAsk AstroTutorSave questionWhich ONE of the following elements is TYPICALLY NOT included in a test progress report?AObstacles and their workaroundsBA detailed assessment of product qualityCTest metrics to show the current status of the test processDNew or changed risksShow AnswerAnswerExplanationA test progress report is used during testing to communicate current test status, metrics, impediments, and emerging or changed risks. A detailed assessment of product quality is typically included in a test completion or summary report, which evaluates testing and product quality at the end of the activity.Learn moreISTQB Certified Tester Foundation Level Syllabus v3.1.1Show comments0Show commentsCommunity DiscussionNo comments yet. Be the first to start the discussion!