QuestionQ63Verified/Chapter 5: Managing the Test ActivitiesCopy linkReport a problemAsk AstroTutorSave questionWhich of the following lists two defined risk-response actions that help control product risk?ADeny risk, Mitigate risk by testingBAccept risk, Abandon riskCAbandon risk, Delay riskDTransfer risk, Accept riskShow AnswerAnswerExplanationProduct-risk control can use several response options, including risk mitigation by testing, risk acceptance, risk transfer, and a contingency plan. Risk transfer and risk acceptance are therefore both defined actions for controlling product risk.Learn moreISTQB Certified Tester Foundation Level Syllabus v4.0.1Show comments0Show commentsCommunity DiscussionNo comments yet. Be the first to start the discussion!