QuestionQ59

VerifiedChapter 4: Test Analysis and Design

Consider these examples of risks identified across different software development projects:

[I]. The expected workloads may be impossible to generate for performance testing because the machines (load injectors) intended to produce those workloads have inadequate hardware equipment.

[II]. A web-application user session is not invalidated after the user has been inactive for a certain period, as configured by the system administrator.

[III]. By the time test design and analysis activities are scheduled to start under the test plan, the test team will not have an adequate requirements specification because many requirements will still be missing.

[IV]. After a failure, the system cannot continue to maintain its pre-failure operation, and some data is corrupted.

Which of the following statements is TRUE?

Explanation

Project risks concern management and control of the project, including poor tool support and delayed delivery of work products. Product risks concern product quality characteristics. Inadequate load-injector hardware and an incomplete requirements specification are project risks; an unenforced session timeout is a security vulnerability, and loss of operation with corrupted data is a reliability and integrity risk in the product.