QuestionQ30

VerifiedChapter 5: Managing the Test Activities

For every test case that must be executed, the table below defines its dependencies and the required test-environment configuration for executing that test case:

Question Image

Assume CONF1 is the test environment’s initial configuration. Based on this assumption, which of the following test-execution schedules satisfies the specified dependencies while minimizing the number of switches between the different test-environment configurations?

Explanation

TC4 and TC3 can be executed in CONF1, with TC4 preceding TC3 because TC3 depends on it. After one switch to CONF2, TC2 can run because TC4 is complete, and TC1 can precede TC5. This satisfies every dependency using only one configuration change.