QuestionQ19

VerifiedChapter 5: Managing the Test Activities

You are a tester on a critical project. Based on the risk analysis, you must determine the test-execution order. Which of the following lists the correct test-execution sequence? Priority 1 is the highest, and Priority 3 is the lowest.

Question Image

Explanation

A dependent test cannot be executed before the test it depends on. Test D must precede Test B, and Test A must precede Test C. Once Test D has run, Test B is executed next because it has the highest priority. The remaining tests then run as Test A followed by Test C.