You are calculating an estimate for a project. Your manager, who is regarded as an estimation expert, has provided these values:

  • Optimistic = 35 days
  • Likely = 40 days
  • Pessimistic = 65 days

Using the three-point estimation technique, what is the correct expression for the final estimate?

Explanation

The three-point PERT estimate is calculated as (E = (O + 4M + P) / 6), and its standard deviation is (SD = (P - O) / 6). For 35, 40, and 65 days, these calculations produce an expected estimate of 43.3 days and a standard deviation of 5 days.