QuestionQ72
VerifiedThe Technical Test Analyst's Tasks in Risk-Based TestingA project has started to replace your company’s sales and merchandising system. The legacy system remains in production, but it is poorly documented and costly to maintain; changes to it have frequently resulted in a large number of defects. The new version will be built using modern techniques and technology.
Requirements include:
- Loading sales data, transmitted electronically from the stores each evening, into a central database, where it is available to other applications.
- Generating sales reports for the merchandisers, whose role is to manage stock levels in stores.
- Forecasting future demand for every product, based on a combination of sales history and forecasting parameters.
Requirements 1 and 2 are met by the current system and will be rewritten without significant change. Requirement 3 is new: these forecasting reports will run overnight, and users will request them by entering simple parameters online during the day.
The sales data are loaded in an overnight batch run. At peak periods, this run has taken longer than scheduled, preventing dependent jobs from completing before the working day begins.
As a Technical Test Analyst, you have been asked to contribute to the project’s Master Test Plan. The key stakeholders are:
- The Merchandising Manager, who requires parameter entry to be quick and easy.
- The Data Centre Manager, who requires the new batch jobs to take less time than the old ones.
No specific performance requirements have been provided for either the batch jobs or online parameter entry.
Which TWO of the following will BEST satisfy the stakeholders’ objectives?