A project developing a new system identifies performance efficiency as a critical requirement. Which option describes how and when the Technical Test Analyst should FIRST participate in performance-test activities for the new system?

Explanation

For critical performance-efficiency requirements, early code reviews of database interactions, component interactions, and error handling can expose performance defects such as inefficient queries and problematic wait-and-retry logic. ISTQB guidance states that such reviews should be scheduled as early as possible, whereas execution of performance load tests is typically performed during system testing in a representative environment.