QuestionQ74
VerifiedThe Tasks of the Test Analyst in Risk-Based TestingYou have been working in an Agile model on a large software project. You developed a traceability matrix that records the risk for each requirement and maps it to the test case that tests that requirement. You have just received a new release in which developers have classified some areas as “high risk” for regression. Consider the following risk table (1 = highest risk):

Based on this information, in what sequence should the test cases be run to help mitigate regression risk?