QuestionQ74

VerifiedThe Tasks of the Test Analyst in Risk-Based Testing

You have been working in an Agile model on a large software project. You developed a traceability matrix that records the risk for each requirement and maps it to the test case that tests that requirement. You have just received a new release in which developers have classified some areas as “high risk” for regression. Consider the following risk table (1 = highest risk):

Question Image

Based on this information, in what sequence should the test cases be run to help mitigate regression risk?

Explanation

Regression-risk priority requires executing the risk-1 test cases as early as their dependencies allow. Test case 3 requires test case 1, and test case 4 requires test case 5, which requires test case 1. This makes the dependency-respecting order 1, 3, 5, 4, followed by test case 2, which has lower regression priority.

Community Discussion

No comments yet. Be the first to start the discussion!