Per the ISTQB Foundation Level syllabus, in the V-model, test design and implementation for each test level begins as soon as the relevant test basis (such as requirements specifications, design documents, or user stories) becomes available. This allows testers to begin creating test cases and identifying defects early, even before the corresponding code is written, embodying the early testing principle that defects found earlier in the lifecycle are cheaper and easier to fix. The other options describe unrelated project phases: project initiation is too early (no test basis exists yet), and the completion of implementation/code release corresponds to test execution, not test design and implementation.