QuestionQ60

VerifiedTest Automation Reporting and Metrics

You have been asked to implement test automation for a project that is failing to meet its deadlines. Further analysis shows that the manual testers cannot keep pace with testing new features because regression testing takes 75% of their time. Consequently, new features are released with many defects, and customers are complaining about the quality.

Given this information, which metric SHOULD you track to demonstrate the value of test automation for this project?

Explanation

Equivalent Manual Test Effort measures the manual time and effort that the automated regression tests replace. It directly demonstrates whether automation frees testers from the regression workload so they can test new features more thoroughly, helping reduce releases with defects and improve delivery performance.