The following exit criteria are defined in the test plan for a software product:

  • EX1. The product test suite must ensure that every quality risk item is covered by at least one test case (a quality risk item may be covered by more than one test case).
  • EX2. Every test case in the test suite must be executed during the execution phase.
  • EX3. Defects are categorized as either "C" (critical defect) or "NC" (non-critical defect). At the end of the test execution phase, the product must have no known C defects.

Which of the following information is not useful when evaluating the specified exit criteria?

Explanation

Evaluating these exit criteria requires evidence of risk-to-test-case coverage, execution status for every test case, and the classification of open defects to confirm that no critical defects remain. A trend chart of elapsed time from defect reporting to resolution measures defect-management responsiveness, but it provides no evidence for any of those three exit criteria. The ISTQB CTFL syllabus identifies traceability as support for coverage evaluation and recognizes test logs and defect reports as test-execution work products.