QuestionQ45

Managing the Test Activities

Which of the following statements concerning the TMMi test process improvement model is true?

K2 1 credit -

  • A In TMMi all the process areas at lower levels must be 75% complete by achieving specific and generic goals in order to claim the higher level
  • B TMMi provides an approach for test process improvement such as the IDEAL (Initiating, Diagnosing, Establishing, Acting and Learning) model
  • C TMMi has a staged architecture for process improvement with seven maturity levels
  • D At TMMi level 1 testing is chaotic without a defined process, and it is often seen as the same as debugging
Explanation

At TMMi maturity level 1, testing is chaotic and undefined, with no defined process areas. Testing and debugging are commonly interleaved or conflated at this level; they become clearly differentiated at level 2. TMMi has five maturity levels and is a reference framework rather than a prescribed improvement approach such as IDEAL. TMMi Framework R1.3